a

Past Jobs

Past Jobs

Past Jobs

Kerr McGee:

Gunnison: Pre-commissioned and commissioned the platform
Gunnison: Performed all well hook-ups (on-going)
Gunnison: Installed lact units
Gunnison: Installation of booster skids offshore
Gunnison: Regular maintenance crew
Nansen: Installation and upgrade of the compressor packages
Nansen: Regular maintenance crew
Nansen: Changed out all Auto-clave tubing to 2507 tubing
Boomvang: Repaired all fire damage on compressors and remainder of platform damage (both electrical & pneumatic)

Hunt Petroleum:

High Island Regular maintenance electricians
EC-76: Designed and installed all electrical power and safety systems
SMI-40: Complete installation of all electrical power and safety systems
SMI-40: Designed and installed logic control systems
WC-485: Refurbished all power systems and cutover new generator pkg. SMI-142: Regular maintenance techs
EI-309: Regular maintenance techs
VERM-248: Regular maintenance techs
WC-485: Complete rebuild of pneumatic and electrical systems.

Parker Drilling:

Rig #262L: Installed all power and SCR systems on the world’s largest land rig
Rig #262L: Commissioned and trained Russian personnel to operate platform
Rig #262L: Continuing rig upgrades
Barge #53: Refurbished rig electrical power and safety systems for operation

HRI:

Rig 178E: Commissioned rig and trained foreign personnel on rig operation

Transocean:

Rather: Installed all electrical systems and control panel for mud pump upgrades

Varco:

BP/Holstein: Pre-commission of drilling rig
BP/Holstein: Commissioned drilling rig and performed QA/QC
BP/Holstein: Installation of rig power and safety systems

Pride Drilling:

BP/Mad Dog: Pre-commission of drilling rig
BP/Mad Dog: Commissioned drilling rig and performed QA/QC
BP/Mad Dog: Installation of rig power and safety systems

Shaw Group:

PEMEX/Lobina: Installation of all electrical, telecommunication and pneumatic systems. Performed start-up and commissioning.
Med/waste Incinerator: Installation of electrical, pneumatic and PLC control systems
General waste Incinerator: Installation of electrical, pneumatic and PLC control systems

Shaw Group:

Energy Production: Installation of electrical, pneumatic and communication systems
Aggreko: Assisted in the layout and cut over of temporary power systems for Hunt Petroleum
Aggreko: Helped design and implement HVAC portable systems

Aggreko: Assisted in emergency power supply from Katrina damage in New Orleans. Assisted in rebuilding the entire power fleet.

DFC: Helped in the design and estimation of production systems for Petrobras

Mariner: Rebuilt the entire production facilities for W1,W2 & W3 sites. Complete electrical & pneumatic demolition and install including Pneumatic Panel installation, MCC rebuild, generator power installation and the complete pneumatic and electrical safety system.
SMI-137: Hurricane damage repair. Completed upgrade of the electrical systems.

Vermillion 261: Design, fabrication and installation of PLC controlled LACT unit

Devon Energy: Complete demolition and reconstruction of all platforms in the Eugene Island fields. This is inclusive of all pneumatic and electrical systems.

Sojitc: Assisted in the upgrade of current platforms in the central Gulf of Mexico.

Apache: Troubleshooting various electrical problems in all fields of the Gulf of Mexico.

TPIC: Upgrade of the Avery Island plant facilities, both pneumatic and electrical upgrade. Repaired storm damage systems from Katrina.

W&T Offshore: Pneumatic panel revisions and upgrade of the W&T Eugene Island fields.

Diamond Offshore:

Diamond Offshore: Electrical installation & commissioning on the Ocean New Era.

Diamond Offshore: Electrical installation & commissioning on the Ocean Concord.

Diamond Offshore: Electrical installation & commissioning on the Ocean Yorktown.

Diamond Offshore: Electrical installation & commissioning on the Ocean Valiant.

Diamond Offshore: Electrical installation & commissioning on the Ocean Ambassador.

Diamond Offshore: Electrical installation & commissioning on the Ocean Quest.

Diamond Offshore: Electrical installation & commissioning on the Ocean Titan

Diamond Offshore: Electrical installation & commissioning on the Ocean Nugget

Anglo-Suisse: Numerous upgrades on offshore installations

Hornbeck: HOS Corral,Antera Commissioning and final coast guard checkout.

HOS, Cantelina: Commissioning, electrical installation and coast guard inspection.

Petrologistics:

Choctaw Plant: Panel design and installation. Field installation and final
checkout.

Lee-Vac: Electrical installation of six new work boats for offshore sights.

Parker Drilling: Complete installation of all power and safety systems for the two mobile land rigs 272 & 273 on the north slope.

Anadarko: Pneumatic upgrades on Boomvang & Nansen platforms.


Energy XX1: Installation of all pneumatic safety systems in the Main Pass
And West Delta fields.


Seadrill: Installed fire & gas systems for the Oberon and Intrepid in
Mexico.

Energy XX1: Completed several construction projects in the west delta fields
And main pass. Working on SMI and south pass fields as well.
We have regular 7&7 guys in various fields

Enterprise Working on meter skids and DRA skids in the ship shoal fields.
We have successfully upgraded the MCC and commissioned both pneumatic and electrical installation. We completed the commissioning of SMI 105.

Enbridge: Completed the installation of three new generators and power systems on SS 332 B.

Nuclear Power Plant
David Bese
Nuclear Plant

Kone Cranes: Removed and replaced the existing overhead cranes. Removed and replaced all the existing power and replaced with new power system. We commissioned the system for duty.

Steel America Norfolk Virginia U.S.Navy completely installed stand-alone crane with all controls and power requirements.

Energy XX1 Walk down and produce all electrical one-line drawings on production platforms. Engineer review and stamp for BSEE approval.

Renaissance Walk down and produce all electrical one-line drawings on production platforms. Engineer review and stamp for BSEE approval.

W&T Offshore Walk down and produce all electrical one-line drawings on production platforms. Engineer review and stamp for BSEE approval.

ECCO has not only completed all projects on time but, also with an outstanding safety record. ECCO has an outstanding safety record with over 3 million-man hours. We are rated an A rating with all our customers.

Safety record is available upon request.

Some of Our Services

ROAD TO SUCCESS

ROAD TO SUCCESS

Quarterly and annual safety awards
Ongoing training
Daily safety meetings
JSA
Jobs are TASK driven
Hazardous assessment reports
Monthly Safety and attendant drawings on long-term projects
Experienced craftsmen